Storm Sewer Installation and Concrete Work Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued the placement of storm sewer along the project area. The contractor has also begun concrete pouring for sidewalks, curbs & gutters.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will continue with the storm sewer installation. Preparations, framing, and pouring of concrete for sidewalks, driveway aprons, curb & gutter will also continue, contributing to the overall advancement of the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Wolf Road Sidewalk Project

Subscribe now to keep reading and get access to the full archive.

Continue reading