Week in Review: Accomplishments and Progress
This past week, the contractor continued placing storm sewer along Wolf Road and worked on framing and pouring sidewalk, as well as curb and gutter. Pedestrian signal foundations were installed throughout the project. AT&T’s subcontractor monitored and protected their utilities during nearby work, and Nicor Gas addressed a damaged gas service.
Looking Ahead: Planned Activities
Next week, the contractor will proceed with storm sewer installation, sidewalk, and curb and gutter work. Nicor Gas and AT&T’s subcontractor will remain on-site to adjust and safeguard utilities, ensuring smooth progress.
Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.
Community Impact: What to Expect
As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.