Final Restoration and Project Progress

Week in Review: Accomplishments and Progress

This past week, the contractor placed hot mix asphalt throughout the project area and completed seeding and blanketing in designated locations. Parking lot wheel stops were installed at the Briarwood parking lot. Additionally, Nicor continued restoration work at various locations where their utility work was performed.

Looking Ahead: Planned Activities

Next week, the contractor plans on addressing punch list items and completing seeding and blanketing. Pavement striping is also scheduled to be finalized across the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.