Pavement Markings and Tree Placement Progress

Week in Review: Accomplishments and Progress

This past week, the contractor installed signs at Camp McDonald and removed old pavement markings, replacing them with new ones throughout the project. Seeding and blanketing continued, and trees were planted across the project area, enhancing the completed sections.

Looking Ahead: Planned Activities

Next week, the contractor plans on placing mulch and bracing newly planted trees, completing topsoil, seed, and blanket placement, and finalizing pavement markings throughout the project. Punch list items will also be addressed to ensure project completion.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.