Landscaping and Project Updates

Week in Review: Accomplishments and Progress

This past week, the contractor placed mulch and braced the newly planted trees throughout the project area. Topsoil, seed, and blanket were placed, enhancing landscaping and restoration efforts. Changeable message boards were removed, and progress was made on completing punch list items.

Looking Ahead: Planned Activities

Next week, Nicor Gas plans to continue restoration work in areas affected by their completed utility work throughout the project. Additionally, pavement markings are anticipated to be placed.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.