ADA Sidewalk Compliance and Railroad Updates

Week in Review: Accomplishments and Progress

This past week, the contractor was on-site removing and replacing sidewalk sections to ensure ADA compliance.

Looking Ahead: Planned Activities

Next week, the contractor will focus on stabilization around the newly replaced sidewalk and general site cleanup.

CN Railroad began railroad improvements at the Wolf Road crossing on February 11, 2025, and expects to complete pedestrian gate installation in May. Sidewalk work at the railroad is anticipated to be completed in June, pending CN Railroad’s schedule.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Discover more from Wolf Road Sidewalk Project

Subscribe now to keep reading and get access to the full archive.

Continue reading