Wolf Road Sidewalk Project Update: Work Suspended

Work on the Wolf Road Sidewalk Project has been temporarily suspended. The contractor is awaiting the completion of Canadian National Railway Company’s work before finishing the sidewalk leading up to the railroad tracks. This remaining work is anticipated to take place this winter, or possibly in early spring.

Thank you for your patience as we coordinate this final stage of the project. Further updates will be provided as more information becomes available.

Landscaping and Project Updates

Week in Review: Accomplishments and Progress

This past week, the contractor placed mulch and braced the newly planted trees throughout the project area. Topsoil, seed, and blanket were placed, enhancing landscaping and restoration efforts. Changeable message boards were removed, and progress was made on completing punch list items.

Looking Ahead: Planned Activities

Next week, Nicor Gas plans to continue restoration work in areas affected by their completed utility work throughout the project. Additionally, pavement markings are anticipated to be placed.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Pavement Markings and Tree Placement Progress

Week in Review: Accomplishments and Progress

This past week, the contractor installed signs at Camp McDonald and removed old pavement markings, replacing them with new ones throughout the project. Seeding and blanketing continued, and trees were planted across the project area, enhancing the completed sections.

Looking Ahead: Planned Activities

Next week, the contractor plans on placing mulch and bracing newly planted trees, completing topsoil, seed, and blanket placement, and finalizing pavement markings throughout the project. Punch list items will also be addressed to ensure project completion.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Final Restoration and Project Progress

Week in Review: Accomplishments and Progress

This past week, the contractor placed hot mix asphalt throughout the project area and completed seeding and blanketing in designated locations. Parking lot wheel stops were installed at the Briarwood parking lot. Additionally, Nicor continued restoration work at various locations where their utility work was performed.

Looking Ahead: Planned Activities

Next week, the contractor plans on addressing punch list items and completing seeding and blanketing. Pavement striping is also scheduled to be finalized across the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Completion and Pedestrian Signal Activation

Week in Review: Accomplishments and Progress

This past week the contractor completed the placement of storm sewer along Wolf Road and continued prepping and pouring sidewalks, driveways, and curb & gutter. Parkway grading and topsoil placement were completed throughout the project, and hot mix asphalt driveways and patches were placed as planned. Pedestrian push buttons, pedestrian signals, and detection were activated at Edward Road, Camp McDonald Road, Old Willow Road, and Palatine Frontage Road.

AT&T began adjusting a manhole in the sidewalk north of Edward Road, while Nicor continued landscape restoration and roadway pavement patching adjacent to their work.

Looking Ahead: Planned Activities

Next week, the contractor will finalize driveway placements and complete seeding and blanketing. Pavement striping is also scheduled throughout the project. AT&T is set to complete the manhole adjustment north of Edward Road, and Nicor plans to finish landscape restoration and roadway pavement patching.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Sidewalk Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued storm sewer installation along Wolf Road and graded parkways in preparation for topsoil. Sidewalks and driveways were prepped and poured at various locations throughout the project. Nicor Gas was on-site, adjusting utilities to support ongoing storm sewer work.

Looking Ahead: Planned Activities

Next week, the contractor will continue placing storm sewer along Wolf Road, grading parkways for topsoil, and preparing and placing sidewalks across the project area. Nicor Gas will remain on-site to adjust utilities, facilitating continued construction progress.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Parkway Preparation Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road and worked on grading parkways for topsoil. Sidewalks, driveways, and curb & gutter were also prepped and poured, making substantial progress across the project.

Looking Ahead: Planned Activities

Next week, the contractor will continue storm sewer installation along Wolf Road and continue grading parkways for topsoil. Plans include placing topsoil, seed, and blanket in completed areas, as well as further preparation and placement of sidewalks throughout the project area.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Parkway Grading Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road and focused on cleaning up and removing debris from the site. Parkway grading for topsoil preparation was also underway. Comcast’s subcontractor was present to monitor and protect their utilities during storm sewer work, while Nicor Gas adjusted their utilities to support ongoing construction.

Looking Ahead: Planned Activities

Next week, the contractor plans to continue grading parkways for topsoil and preparing to place sidewalks throughout the project. Nicor Gas will remain on-site to adjust their utilities, facilitating further storm sewer installation. Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Pedestrian Signal Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road and worked on framing and pouring sidewalk, as well as curb and gutter. Pedestrian signal foundations were installed throughout the project. AT&T’s subcontractor monitored and protected their utilities during nearby work, and Nicor Gas addressed a damaged gas service.

Looking Ahead: Planned Activities

Next week, the contractor will proceed with storm sewer installation, sidewalk, and curb and gutter work. Nicor Gas and AT&T’s subcontractor will remain on-site to adjust and safeguard utilities, ensuring smooth progress.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road and began framing and pouring sidewalk, as well as curb and gutter. Both AT&T and ComEd’s subcontractors were on-site, adjusting their utilities to enable ongoing storm sewer installation.

Looking Ahead: Planned Activities

Next week, the contractor will continue installing storm sewer, sidewalk, and curb and gutter throughout the project. Nicor Gas, along with AT&T’s subcontractor, will be on-site adjusting and protecting utilities to support the project’s progress.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.