Pavement Removal and Inlet Protection Installation Progress


Week in Review: Accomplishments and Progress

This past week, the contractor initiated the installation of inlet and pipe protection around existing flared end sections and began the removal of sidewalks, as well as curb and gutter systems.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to complete the installation of inlet and pipe protection. This critical step ensures the water management systems continue to function efficiently.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Safety Signage Repair; Upcoming Inlet Protection Installation and Pavement Removal


Week in Review: Accomplishments and Progress

This past week, the contractor successfully repaired a “Road Construction Ahead” sign on Edward Rd.

Looking Ahead: Planned Activities

This coming week, the contractor plans on placing inlet and pipe protection around existing flared end sections, a critical step to ensure our water management systems remain in good working order. Additionally, the contractor anticipates beginning the removal of sidewalks, driveway aprons, and curbs & gutters.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Silt Fence Installation Complete; Tree Trunk and Inlet Protection In Progress

Week in Review: Accomplishments and Progress

This past week, the contractor completed the installation of silt fencing across the entire project area, a crucial step in ensuring controlling sediment runoff. Additionally, the contractor began installing tree trunk protection, reflecting a commitment to preserving the natural landscape during construction activities.

Looking Ahead: Planned Activities

The upcoming week will see continued progress, with the contractor set to begin installing inlet and pipe protection around existing flared end sections. This work is essential for maintaining local waterways and minimizing the impact of construction runoff.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Tree Clearing Complete and Silt Fence Installation Progress

Week in Review: Accomplishments and Progress

The contractor successfully completed tree removal and clearing within the project area this past week, marking a significant step forward in the project timeline. This accomplishment paves the way for further progress. Additionally, the initial phase of installing silt fence throughout the project site has begun.

Looking Ahead: Planned Activities

In the coming week, the contractor is expected to finalize the installation of silt fencing across the entire project area. These fences play a crucial role in controlling sediment runoff and protecting water quality.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Saw Cutting Progress and Upcoming Tree Clearing

Week in Review: Accomplishments and Progress

This past week the contractor continued with saw-cutting operations for the removal of driveway aprons, sidewalks, curbs, gutters, and pavement patching throughout the project area. These crucial steps pave the way for a smoother and more efficient construction process.

Looking Ahead: Planned Activities

Tree removal and clearing are scheduled for completion this week. Additionally, the installation of silt fencing is anticipated to commence across the project area. This action is a key step in our commitment to environmental sustainability, ensuring effective erosion control and the protection of the surrounding landscape as our work continues.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as we work to improve the community’s infrastructure. We encourage residents to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Inlet Basket Installations and Saw Cutting Operations Underway

Week in Review: Accomplishments and Progress

The week saw the successful installation of inlet baskets, a critical component in managing stormwater and preventing debris from entering drainage systems. This step is vital for both environmental protection and the reduction of water-related issues on our roads and properties.

In addition to the installation of inlet baskets, the contractor began saw-cutting operations. This preparatory work is essential for the upcoming removal of driveway aprons, sidewalks, curbs, gutters, and pavement patching. These efforts are foundational to the overall project, ensuring a smoother and more efficient reconstruction process.

Looking Ahead: Planned Activities

As we move into next week, the contractor is set to begin installation of silt fences across the project area. This measure is crucial for erosion control, safeguarding the surrounding environment as construction progresses. Saw-cutting operations will also continue. This ongoing work is key to preparing the site for the subsequent phases of the Wolf Road Sidewalk Project.

Community Impact: What to Expect

Residents should be aware of the neighborhood impacts during this time. Possible lane closures may occur, leading to delays in the area. Your patience and understanding are appreciated as we work to improve the community’s infrastructure. We encourage residents to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Signage and Prep Work Complete: Construction Begins Next Week

This past week marked the start of the Wolf Road Sidewalk Project, with several key activities underway. Signage placement has started along the project area, enhancing visibility and safety for all. The contractor’s layout work has kicked off, laying the groundwork for the upcoming construction phases. We’ve also completed the maintenance transfers for the traffic signals, ensuring that our infrastructure remains operational. Additionally, we’re expecting the placement of message boards by Saturday, March 23rd, further improving communication and guidance for residents and commuters.

Looking ahead to next week, we have a busy schedule planned. The contractor is set to install inlet baskets and silt fences across the project area, a crucial step in managing stormwater and protecting local waterways. Saw cutting activities are also on the agenda, preparing for the removal of driveway aprons, sidewalks, and curb and gutter sections. This preparation is essential for the subsequent construction work. Additionally, tree and brush removal will begin, clearing the way for further project developments.

Residents should be aware of the neighborhood impacts during this time. Possible lane closures may occur, leading to delays in the area. We appreciate your patience and understanding as we work to improve the community’s infrastructure. Your cooperation and support are invaluable to us.

Welcome!

On behalf of the City of Prospect Heights we would like to welcome you to the project website for the Wolf Road Sidewalk Construction project. This sidewalk project is part of the City of Prospect Height’s continued initiative to improve the infrastructure throughout the community and is necessary to improve pedestrian accessibility within the City.

This project will be completed along Wolf Road, from Edward Road / Metra Station to Palatine Frontage Road for a total distance of 1.21 miles in the City of Prospect Heights, Cook County.

This project is scheduled to begin March 25, 2024, weather permitting, and we anticipate the project being substantially completed in early August 2024. Weather and unforeseen circumstances may adversely affect the proposed schedule.

The construction operations will likely create delays in travel, and motorists should allow extra time through the area. During working hours, two-way traffic will be maintained over one lane of pavement and be controlled with certified flaggers. Access to all homes will be maintained, whether by temporary stone ramps or permanent pavement. As with any construction project, there will occasionally be inconveniences you may experience when traveling through the area, but the City and Contractor are working together to minimize the disruptions and nuisances.

In accordance with the City of Prospect Heights, daily working hours for the construction project are from 7:00 AM to 6:00 PM Monday through Saturday. There is currently no work anticipated on Sundays or legal, observed holidays.