Pavement Removal and Storm Sewer Installation Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued removing sidewalks and curb & gutter throughout the project. Topsoil stripping began along the project, and driveway aprons were removed, with temporary stone placed to maintain access. Additionally, storm sewer installation started north of Edward Road (Metra Station entrance).

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to continue placing storm sewer along the project and removing driveway aprons throughout the area.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.