Storm Sewer Installation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer and framing for sidewalk along Wolf Road. The handhole south of Camp McDonald Road was removed, and both AT&T and ComEd’s subcontractors were on-site protecting and adjusting utilities, allowing for storm sewer installation to proceed.

Looking Ahead: Planned Activities

Next week, the contractor will continue placing storm sewer and sidewalk. Nicor Gas, AT&T, and ComEd’s subcontractors will remain on-site to adjust and protect their utilities, ensuring smooth progress for the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Traffic Signal Improvements Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road and performed traffic signal improvements at various intersections. Nicor Gas was on-site adjusting utilities, and AT&T’s subcontractor monitored their utilities while the contractor worked nearby. Some driveway apron installations remain pending in Nicor’s work zone.

Looking Ahead: Planned Activities

Next week, storm sewer installation is planned to continue along Wolf Road, as well as sidewalk, curb, and gutter placement. Nicor Gas and AT&T’s subcontractor plans to remain on-site to support utility adjustments and protections.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Utility Coordination Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road and applied topsoil, seed, and blanket in completed areas. Nicor Gas was on-site adjusting utilities, while AT&T supported their cable and conducted potholing to avoid conflicts with the proposed storm sewer. A bus shelter at the southeast corner of Wolf Road and Piper Lane was temporarily removed due to storm sewer work and will be relocated once completed.

Looking Ahead: Planned Activities

Next week, the contractor will continue storm sewer placement, sidewalk, and curb & gutter work. Nicor Gas will also maintain utility adjustments to support progress.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along Wolf Road. Nicor Gas remained on-site adjusting utilities, allowing further progress on the storm sewer installation. ComEd completed the removal of bracing on a utility pole at the north end of the project after storm sewer work in that area was finished.

Looking Ahead: Planned Activities

Next week, the contractor will place topsoil, seed, and blanket in completed areas and continue storm sewer installation. Nicor Gas will maintain utility adjustments to facilitate ongoing construction.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Silt Fence Installation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor focused on placing silt fences around stockpiles throughout the project site to manage sediment control. Nicor Gas continued adjusting its utilities, allowing the contractor to proceed with the planned storm sewer installation. Some driveway aprons remain on hold in Nicor’s work zone.

Looking Ahead: Planned Activities

In the coming week, the contractor will place topsoil, seed, and blanket in completed areas and continue storm sewer installation along Wolf Road. Nicor Gas and ComEd will continue their respective utility adjustments, with ComEd supporting storm sewer work by bracing a utility pole at the north end of the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Concrete Sidewalk Installation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing concrete sidewalks, driveway aprons, and curb & gutter at Old Willow Road. Additionally, inlet and pipe protection were installed, and inlet filters were cleaned to ensure proper drainage. Nicor Gas remained on-site adjusting utilities, with some driveway aprons awaiting placement in their work zone.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will place topsoil, seed, and blanket in completed areas. Storm sewer installation along Wolf Road will continue. Nicor Gas will proceed with utility adjustments, and ComEd will continue bracing an existing utility pole to allow further storm sewer work at the north end of the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Sidewalk Preparation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued preparing concrete sidewalks and driveway aprons at Old Willow Road. Progress was made connecting sump pump discharges to the proposed storm sewer system. Nicor Gas remained on-site adjusting utilities, with some driveway apron installations pending in their work zone.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will place topsoil, seed, and blanket in completed areas. Concrete pouring for sidewalks and driveway aprons at Old Willow Road will continue. Nicor Gas will continue with utility adjustments, and ComEd will continue bracing a utility pole to enable further storm sewer work at the north end of the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Concrete Sidewalk Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued preparing, framing, and pouring concrete sidewalks and driveway aprons. Storm sewer placement continued along Wolf Road, near Old Willow Road. Nicor Gas remained on-site adjusting utilities, with some driveway aprons awaiting completion in their work zone.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will place topsoil, seed, and blanket in areas where construction has been completed. Work will continue on preparing, framing, and pouring concrete sidewalks. Storm sewer installation will proceed along Wolf Road, with ComEd bracing a utility pole to facilitate work. Nicor Gas will also continue adjusting its utilities.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Concrete Work and Asphalt Paving Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued preparing, framing, and pouring concrete sidewalks and driveway aprons. Concrete traffic signal post foundations were poured, and sanitary manhole reconstructions were completed. The contractor also paved the first two lifts of asphalt for driveway aprons, a section of the parking lot south of Camp McDonald Rd, and the roadway patching at Edward Rd. Nicor Gas remained on-site, adjusting utilities to allow for continued storm sewer installation, with some driveway aprons awaiting completion in Nicor’s work zone.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will focus on finishing the final lift of asphalt for the driveway aprons, the section of the parking lot south of Camp McDonald Rd, and the roadway patching at Edward Rd. Grading and shaping of ditches will continue, along with the preparation, framing, and pouring of concrete sidewalks. Additionally, storm sewer work at Old Willow Road will resume once Nicor Gas completes utility relocation in the area. Nicor Gas will continue adjusting utilities to support ongoing construction efforts.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Utility Adjustments Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued the placement of storm sewer along the project area. Preparation, framing, and pouring of concrete sidewalks and driveway aprons continued, along with the grading and shaping of ditches. The contractor also framed for pedestrian signal foundations and handholes and began prepping for asphalt driveway aprons. Nicor Gas was on-site adjusting their utilities to facilitate the storm sewer installation.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will continue with the preparation, framing, and pouring of concrete sidewalks and driveway aprons. Grading and shaping of ditches will proceed, and paving asphalt roadway patching at Edward Road will take place. Asphalt driveways south of Camp McDonald Road and residential asphalt driveway aprons along the project will also be paved. Additionally, the section of the parking lot south of Camp McDonald Road will be paved. The contractor plans to pour pedestrian traffic signal post foundations and handholes, and reconstruct sanitary manholes throughout the project. Nicor Gas will continue adjusting their utilities to support the storm sewer installation.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.