Week in Review: Accomplishments and Progress
This past week, the contractor made progress with the placement of storm sewer along the project area. The preparation, framing, and pouring of concrete sidewalks and curb & gutter continued as planned. Additionally, grading and shaping of ditches were carried out throughout the project.
Looking Ahead: Planned Activities
In the upcoming week, the contractor will continue with the preparation, framing, and pouring of concrete sidewalks. Grading and shaping of ditches will proceed, alongside paving asphalt roadway patching at Edward Road and asphalt driveways south of Camp McDonald Road. The section of the parking lot south of Camp McDonald Road will also be paved. Additionally, the contractor plans to begin traffic signal improvements throughout the project.
Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.
Community Impact: What to Expect
As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.