Storm Sewer Installation and Concrete Work Progress

Week in Review: Accomplishments and Progress

This past week, the contractor made progress with the placement of storm sewer along the project area. The preparation, framing, and pouring of concrete sidewalks and curb & gutter continued as planned. Additionally, grading and shaping of ditches were carried out throughout the project.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will continue with the preparation, framing, and pouring of concrete sidewalks. Grading and shaping of ditches will proceed, alongside paving asphalt roadway patching at Edward Road and asphalt driveways south of Camp McDonald Road. The section of the parking lot south of Camp McDonald Road will also be paved. Additionally, the contractor plans to begin traffic signal improvements throughout the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Concrete Work Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued the placement of storm sewer throughout the project area. Concrete sidewalk, driveways, and curb & gutter were prepared, framed, and poured. Grading and shaping of ditches progressed as planned. The traffic signal head at the southeast corner of Edward Road was temporarily relocated to facilitate further storm sewer work.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to:

  • Continue placing storm sewer along the project.
  • Continue with the preparation, framing, and pouring of concrete sidewalks and driveway aprons.
  • Proceed with grading and shaping of ditches throughout the project.
  • Pave asphalt roadway patching at Edward Road.
  • Pave asphalt driveways south of Camp McDonald Road.
  • Pave the section of the parking lot south of Camp McDonald Road.
  • Begin the placement of topsoil, seed, and blanket where applicable, south of Alderman Ave.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Guardrail Removal Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along the project area. They also began connecting sump pumps from parkways into storm sewer structures, enhancing drainage capabilities. Concrete sidewalk and curb & gutter preparation, framing, and pouring progressed steadily. Additionally, the guardrail along the project was removed, making way for further construction activities.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will continue with storm sewer installation. The preparation, framing, and pouring of concrete sidewalks and driveway aprons will also proceed, advancing the project’s overall development.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Concrete Work Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued the placement of storm sewer along the project area. The contractor has also begun concrete pouring for sidewalks, curbs & gutters.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will continue with the storm sewer installation. Preparations, framing, and pouring of concrete for sidewalks, driveway aprons, curb & gutter will also continue, contributing to the overall advancement of the project.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Driveway Apron Removal Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued placing storm sewer along the project, advancing the essential infrastructure work. Sidewalk and curb & gutter preparations for concrete pouring have begun. Additionally, the contractor continued removing driveway aprons and installing temporary access to driveways, ensuring residents maintain accessibility during construction.

Looking Ahead: Planned Activities

In the upcoming week, the contractor will continue storm sewer installation throughout the project area. The preparation of sidewalks and curb & gutter for concrete work will also proceed, along with the ongoing removal of driveway aprons.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Storm Sewer Installation and Topsoil Stripping Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued stripping topsoil along the project area, ensuring a clear path for upcoming work. Additionally, storm sewer installation progressed north of Edward Rd, near the Metra Station entrance.

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to continue the storm sewer installation throughout the project area. Preparations for the proposed sidewalk will also begin on the south end of the project area.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Pavement Removal and Storm Sewer Installation Progress

Week in Review: Accomplishments and Progress

This past week, the contractor continued removing sidewalks and curb & gutter throughout the project. Topsoil stripping began along the project, and driveway aprons were removed, with temporary stone placed to maintain access. Additionally, storm sewer installation started north of Edward Road (Metra Station entrance).

Looking Ahead: Planned Activities

In the upcoming week, the contractor plans to continue placing storm sewer along the project and removing driveway aprons throughout the area.

Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Work Scheduled to Resume this Week

The contractor is scheduled to begin remobilizing materials and equipment, with plans to resume work later this week.

Property owners along the construction area are asked to continue to maintain their parkways in areas undisturbed by active construction, as per the City ordinance. For everyone’s safety, please maintain a safe distance from construction activities and uneven ground.

Future Storm Sewer Work

Week in Review: Accomplishments and Progress

No work was completed this week while IDOT is approving contractor submittals.

Looking Ahead: Planned Activities

The contractor anticipates beginning storm sewer work once IDOT approves contractor submittals.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.

Pipe & Inlet Protection Installation Complete; Site Preparations

Week in Review: Accomplishments and Progress

This past week, the contractor successfully completed the installation of inlet and pipe protection around existing flared end sections across the project area. The contractor also repaired silt fences and cleaned inlet baskets, ensuring environmental protection measures are well maintained. Additionally, barricades were delivered to the project site, preparing for the next stages of construction.

Looking Ahead: Planned Activities

No work is anticipated this week while IDOT is approving contractor submittals.

Community Impact: What to Expect

As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.