Week in Review: Accomplishments and Progress
This past week, the contractor continued preparing, framing, and pouring concrete sidewalks and driveway aprons. Storm sewer placement continued along Wolf Road, near Old Willow Road. Nicor Gas remained on-site adjusting utilities, with some driveway aprons awaiting completion in their work zone.
Looking Ahead: Planned Activities
In the upcoming week, the contractor will place topsoil, seed, and blanket in areas where construction has been completed. Work will continue on preparing, framing, and pouring concrete sidewalks. Storm sewer installation will proceed along Wolf Road, with ComEd bracing a utility pole to facilitate work. Nicor Gas will also continue adjusting its utilities.
Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.
Community Impact: What to Expect
As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.