Week in Review: Accomplishments and Progress
This past week, the contractor continued placing storm sewer along Wolf Road and performed traffic signal improvements at various intersections. Nicor Gas was on-site adjusting utilities, and AT&T’s subcontractor monitored their utilities while the contractor worked nearby. Some driveway apron installations remain pending in Nicor’s work zone.
Looking Ahead: Planned Activities
Next week, storm sewer installation is planned to continue along Wolf Road, as well as sidewalk, curb, and gutter placement. Nicor Gas and AT&T’s subcontractor plans to remain on-site to support utility adjustments and protections.
Residents along the project limits are kindly requested to maintain their parkways in areas not affected by active construction. For safety, please keep a respectful distance from any construction activities or disturbed ground.
Community Impact: What to Expect
As construction continues, residents may experience possible lane closures, which could lead to temporary delays. Your patience and understanding are appreciated as work to improve the community’s infrastructure continues. Residents are encouraged to stay informed about the project’s progress and any anticipated changes in traffic patterns.